Tag: #SeeingOrange

Aug 18
#SeeingOrange Update #16

The following is to provide you with information of what to expect on Route 1 in Biddeford this upcoming week. Please note that this is a projected schedule of what to expect and is subject to change due to weather, work progress and/or other circumstances. Completed: Route 1/ Elm Street: Sewer separation project, which consisted of...

Jul 28
Seeing Orange Update #15

The pavement process on Elm street is finished. The roadwork on Adams and Jefferson are set to begin the week of July 27th. The process will begin with pit tests, which will preempt the installation of a new sewer line. The sewer line is set to be installed the week of August 2nd or the...

Jul 21
Seeing Orange Update #14 Week of July 20th

The following is to provide you with information of what to expect on Route 1 in Biddeford this upcoming week. Please note that this is a projected schedule of what to expect and is subject to change due to weather, work progress and/or other circumstances.

Jul 14
SeeingOrange Update #13

Upper Main Street: The railroad on upper Main Street (past Elm Street) will be replacing a damaged rail section today, Monday, July 13. Road will be closed from Bradbury to Western Ave. Anticipated one day of work, with detours around the area.

Jul 07
Seeing Orange Update #12

Between July 7-14, Maine DOT will finish work on Elm Street (placing manhole covers, frames, and driveway butt joints, as well as conduit installations). Maine Water will finish final work on Elm/Cutts Street in this timeframe as well. During this phase of construction, projects will be in isolated areas. Alternating traffic and short detours will...

Jun 30
SeeingOrange Update #11

  The first phases of construction on Elm Street have been completed. The street has been raised to its original grade and milled. The sewer and water utilities will be raised this week and should be completed by July 7. This will clear the way for the final coat of pavement, which is set to be...

Jun 24
#SeeingOrange #10

There’s an end in site for Elm Street construction! First coat of pavement today, then about five working days to raise the sewer and water structures to grade. Then final coat of pavement, weather permitting, taking about 2 days. ‪Expected completion July 3. The contractor is working with the Police Department to develop and implement...