The first phases of construction on Elm Street have been completed. The street has been raised to its original grade and milled.
The sewer and water utilities will be raised this week and should be completed by July 7. This will clear the way for the final coat of pavement, which is set to be started the week of July 15, with no exact completion date set yet.